Monday 23 June 2014

Project Management

FACULTY OF BUSINESS, ENTERPRISE AND LIFELONG LEARNING
INTERNATIONAL PROGRAMME
ACADEMIC YEAR 2013/14
NOVEMBER – MARCH ASSESSMENT PERIOD
Module Code: BU5602
Module Title: Project Management
Level: 5
Assessment Type: Individual Assignment 1
Maximum Word Limit: 2,000 words
Assessment Weighting: 50%
Submission Date: 19th February 2014
INSTRUCTIONS TO CANDIDATES:
 Prepare the assignment in a word processor document to upload on to the portal.
 Your name and student number should be included in the footer of each page of the
assignment document, and all pages should be numbered.
 Start each question (if there are many) on a new page in the document and provide a
heading for each question. Paginate your document so that it is neatly presented.
 The assignment must be submitted on or before the due date specified by the college.
There are penalties for late submissions.
 Collusion and copying are not allowed. Each assignment must be done entirely by you.
There are severe penalties for copying and collusion including loss of marks in the
assignment, failing the entire subject or dismissal from the course.
 Outside materials may be used in assignments but all such material must be quoted and
referenced if included verbatim. In general you should present your ideas and
understanding in your own words.
PM ASSIGNMENT 1 – COURSE WORK
On successful completion of this module the student will be expected to be able to:
LO1 - Understand and critically comprehend the theory, concepts, practices and role of project management within businesses and organisations and its contribution to business development, business functions and business success
LO2 - Evaluate and critically comprehend the intergrational importance and operational contexts for project management and project planning within organisations and its contribution to strategic direction and business applications
LO3 - Devise and implement a project management plan for an identified organisation and/or business context
LO4 - Understand and demonstrate the importance of team development and delivery within the project management contexts with an organisation
1. Critically evaluate five factors that generally contribute to project failure
(30 marks)
LO1
2. Table 1 indicates the sequence and interdependence of the 10 activities (A – K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table
Table 1
Activity
Description
Duration (wks)
Precedence
A
Requirement Gathering
27
-
B
Business Analysis
24
-
C
Systems Analysis
21
-
D
Coding
21
A
E
Unit Test
22
B
F
Module Testing
27
C
G
Systems Testing
22
F
H
User Acceptance Testing
22
G,E
J
Implementation
22
H
K
Handover
23
D, J
(a) Construct a network diagram identifying the following:
i. Earliest Start Time(EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities D, F & J
iv. Critical Path for the project
(40 marks)
b) Assume that there is a delay of 3 weeks in completing activity H. Analyse one action that the Operations Manager could take to avoid exceeding the current length of the critical path. (30 marks)
LO2